Actividad
|
Precedentes
|
Duración
(en semanas)
|
|||||
Optimista
|
Más probable
|
Pesimista
|
Tiempo promedio
Tij
|
Desviación estándar
ᵹ ij
|
|||
A
|
Inicio
|
-
|
1
|
2
|
3
|
2
|
0,11111111
|
B
|
Elección del tema
|
A
|
1
|
2
|
3
|
2
|
0,11111111
|
C
|
Análisis del problema
|
B,D
|
2
|
3
|
4
|
3
|
0,11111111
|
D
|
Encuestas
|
A
|
1
|
2
|
3
|
2
|
0,11111111
|
E
|
Elaboración del proyecto
|
C
|
4
|
5
|
6
|
5
|
0,11111111
|
F
|
Gestionar página
|
E
|
4
|
5
|
6
|
5
|
0,11111111
|
G
|
Buscar servidor
|
K
|
1
|
2
|
3
|
2
|
0,11111111
|
H
|
Pedir autorización de la carrera
|
C
|
2
|
3
|
4
|
3
|
0,11111111
|
I
|
Construcción de la caseta
|
H
|
4
|
5
|
6
|
5
|
0,11111111
|
J
|
Contratación del encargado de la
caseta
|
H,I
|
2
|
3
|
4
|
3
|
0,11111111
|
K
|
Diseñar página web
|
F
|
5
|
6
|
7
|
6
|
0,11111111
|
L
|
Publicar página web
|
G,K
|
1
|
2
|
3
|
2
|
0,11111111
|
M
|
Realización de seminarios
|
N
|
12
|
13
|
14
|
13
|
0,11111111
|
N
|
Contratar conferencistas
|
E,H,J,L
|
2
|
2
|
4
|
2,33333333
|
0,11111111
|
|
A
|
B
|
C
|
D
|
E
|
F
|
G
|
H
|
I
|
J
|
K
|
L
|
M
|
N
|
|
V
|
V1
|
V2
|
V3
|
V4
|
V5
|
V6
|
V7
|
V8
|
V9
|
A
|
0
|
1
|
0
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
|
2
|
2
|
2
|
2
|
2
|
2
|
2
|
2
|
2
|
0
|
B
|
0
|
0
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
|
1
|
1
|
1
|
1
|
1
|
1
|
1
|
1
|
0
|
*
|
C
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
|
2
|
2
|
2
|
2
|
2
|
1
|
1
|
0
|
*
|
*
|
D
|
0
|
0
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
|
1
|
1
|
1
|
1
|
1
|
1
|
1
|
1
|
0
|
*
|
E
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
|
2
|
2
|
1
|
1
|
1
|
1
|
0
|
*
|
*
|
*
|
F
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
0
|
|
1
|
1
|
1
|
1
|
1
|
0
|
*
|
*
|
*
|
*
|
G
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
|
1
|
1
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
*
|
H
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
1
|
0
|
0
|
0
|
1
|
|
3
|
3
|
2
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
I
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
0
|
0
|
|
1
|
1
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
*
|
J
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
|
1
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
K
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
0
|
0
|
1
|
0
|
0
|
|
2
|
2
|
2
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
L
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
|
1
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
M
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
|
0
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
N
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
|
1
|
0
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
*
|
NIVEL
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
|||||||||||||||
ACTIVIDAD
|
M
|
N
|
J
|
G
|
H
|
F
|
E
|
C
|
B
|
A
|
|||||||||||||||
|
|
|
L
|
I
|
K
|
|
|
|
D
|
|
Tiempo de duración del proyecto 41 semanas
ACTIVIDADES DE LA RUTA CRÍTICA
|
|
INTERVALO DE
FLOTAMIENTO
|
|
A
|
Inicio
|
0
|
|
B
|
Elección del tema
|
0
|
|
C
|
Análisis del problema
|
0
|
|
D
|
Encuestas
|
0
|
|
E
|
Elaboración del proyecto
|
0
|
|
F
|
Gestionar página
|
0
|
|
G
|
Buscar servidor
|
0
|
|
K
|
Diseñar página web
|
0
|
|
L
|
Publicar página web
|
0
|
|
N
|
Contratar conferencistas
|
0
|
|
M
|
Realización de seminarios
|
0
|
|
Margen total
Margen cierto